[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1111986,787,1,"单选题","炉窑砌筑前工序交接时，不需提交证明书的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","炉子中心线和控制标高的测量记录",false,{"key":16,"text":17,"correct":14},"B","隐蔽工程验收合格证明",{"key":19,"text":20,"correct":14},"C","托砖板焊接质量检查合格证明",{"key":22,"text":23,"correct":24},"D","炉窑出厂或进场检查验收记录",true,"本题考查的是炉窑砌筑前工序交接的规定。工序交接证明书应包括以下内容：（1）炉子中心线和控制标高的测量记录及必要的沉降观测点的测量记录；（2）隐蔽工程的验收合格证明；（3）炉体冷却装置、管道和炉壳的试压记录及焊接严密性试验验收合格的证明；（4）钢结构和炉内轨道等安装位置的主要尺寸的复测记录；（5）动态炉窑或炉子的可动部分的试运转合格的证明；（6）炉内托砖板和铺固件等的位置、尺寸及焊接质量的检查合格的证明；（7）上道工序成果的保护要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]