[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111979,787,1,"单选题","当防潮层采用玻璃纤维布复合胶泥涂抹施工时，立式设备和垂直管道的环向接缝，应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","上下搭接",true,{"key":16,"text":17,"correct":18},"B","两侧搭接",false,{"key":20,"text":21,"correct":18},"C","缝口朝下",{"key":23,"text":24,"correct":18},"D","缝口朝上","本题考查的是防潮层施工技术要求。当防潮层采用玻璃纤维布复合胶泥涂抹施工时，立式设备和垂直管道的环向接缝，应为上下搭接。卧式设备和水平管道的纵向接缝位置，应在两侧搭接，并应缝口朝下。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]