[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111970,787,1,"单选题","自动化仪表施工的原则是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先地下后地上；先土建后安装；先配管布线再安装设备；先两端后中间",false,{"key":16,"text":17,"correct":18},"B","先土建后安装；先安装设备再配管布线；先两端后中间；先地下后地上",true,{"key":20,"text":21,"correct":14},"C","先安装设备再配管布线；先土建后安装；先地上后地下；先两端后中间",{"key":23,"text":24,"correct":14},"D","先土建后安装；先中间后两端；先地下后地上；先安装设备再配管布线","本题考查的是自动化仪表安装主要施工程序。自动化仪表施工的原则是：先土建后安装；先地下后地上；先安装设备再配管布线；先两端后中间。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]