[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1111969,787,1,"单选题","自动化仪表工程施工中，综合控制系统试验的紧后工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投运",false,{"key":16,"text":17,"correct":14},"B","交接验收",{"key":19,"text":20,"correct":14},"C","竣工资料编制",{"key":22,"text":23,"correct":24},"D","回路试验",true,"本题考查的是自动化仪表安装主要施工程序。自动化仪表安装施工程序：施工准备→配合土建制作安装盘柜基础→盘柜、操作台安装→电缆槽、接线箱（盒）安装→取源部件安装→仪表单体校验、调整安装→电缆敷设→仪表管道安装→仪表电源设备试验→综合控制系统试验→回路试验、系统试验→投运→竣工资料编制→交接验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]