[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111965,787,1,"单选题","下列自动化仪表安装施工程序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","取源部件安装→电缆敷设→仪表管道安装→仪表单体校验.调整安装",false,{"key":16,"text":17,"correct":18},"B","取源部件安装→仪表单体校验.调整安装→电缆敷设→仪表管道安装",true,{"key":20,"text":21,"correct":14},"C","取源部件安装→仪表管道安装→电缆敷设→仪表单体校验.调整安装",{"key":23,"text":24,"correct":14},"D","取源部件安装→电缆敷设→仪表单体校验.调整安装→仪表管道安装","本题考查的是自动化仪表安装主要施工程序。自动化仪表安装施工程序的部分施工程序顺序为：取源部件安装→仪表单体校验、调整安装→电缆敷设→仪表管道安装。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]