[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111954,787,1,"单选题","光伏发电设备的安装程序中，光伏组件安装之后，应做的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","汇流箱安装",true,{"key":16,"text":17,"correct":18},"B","逆变器安装",false,{"key":20,"text":21,"correct":18},"C","电气设备安装",{"key":23,"text":24,"correct":18},"D","调试","本题考查的是光伏与风力发电设备的安装技术要求。光伏发电设备的安装程序：施工准备→基础检查验收→设备检查→光伏支架安装→光伏组件安装→汇流箱安装→逆变器→电气设备安装→调试→验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]