[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1111942,787,1,"单选题","液压试验应缓慢分段升压，待达到试验压力后，稳压（ ），再将试验压力降至设计压力，保持（ ），检查压力表有无压降、管道所有部位有无渗漏。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10min，20min",false,{"key":16,"text":17,"correct":18},"B","10min，30min",true,{"key":20,"text":21,"correct":14},"C","30min，10min",{"key":23,"text":24,"correct":14},"D","20min，10min","本题考查的是管道系统试验。试验应缓慢升压，待达到试验压力后，稳压10min，再将试验压力降至设计压力，稳压30min，检查压力表有无压降、管道所有部位有无渗漏。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]