[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111930,787,1,"单选题","架空电力线路安装程序中，立杆的紧后工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","横担安装",false,{"key":16,"text":17,"correct":14},"B","绝缘子安装",{"key":19,"text":20,"correct":21},"C","拉线安装",true,{"key":23,"text":24,"correct":14},"D","导线架设","本题考查的是电力架空线路施工要求。电力架空线路施工工序：（1）熟悉工程图纸，明确设计要求；（2）按施工图计算出工程量，准备材料和机具；（3）现场勘察，测量定位，确定线路走向；（4）按地理情况和施工机械开挖电线杆基础坑；（5）电杆、横担、瓷瓶和各类金具检查及组装；（6）根据杆位土质情况进行基础施工和立杆；（7）拉线制作与安装；（8）放线、架线、紧线、绑线及连线；（9）送电运行验收，竣工资料整理。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]