[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111929":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1111929,787,1,"单选题","电气设备交接试验中，高压试验结束后对直流试验设备及大电容的被测试设备多次放电的放电时间不少于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1min",true,{"key":16,"text":17,"correct":18},"B","2min",false,{"key":20,"text":21,"correct":18},"C","3min",{"key":23,"text":24,"correct":18},"D","5min","本题考查的是电气设备的施工技术要求。高压试验结束后，应对直流试验设备及大电容的被测试设备多次放电，放电时间至少1min以上。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]