[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111920,787,1,"单选题","设备吊装就位的紧后工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备清洗",false,{"key":16,"text":17,"correct":14},"B","设备灌浆",{"key":19,"text":20,"correct":21},"C","设备安装调整",true,{"key":23,"text":24,"correct":14},"D","垫铁安装","机械设备安装的一般程序为：施工准备—设备开箱检查—基础测量放线—基础检查验收—垫铁设置—设备吊装就位—设备安装调整—设备固定与灌浆—零部件清洗与装配—润滑与设备加油—设备试运转—工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]