[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111897,787,1,"单选题","锅炉受压元件安装前，应制定（ ），并进行焊接工艺评定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","焊接工艺评定报告",false,{"key":16,"text":17,"correct":14},"B","焊接作业指导书",{"key":19,"text":20,"correct":21},"C","焊接工艺评定作业指导书",true,{"key":23,"text":24,"correct":14},"D","焊接施工方案","本题考查的是焊接工艺评定。锅炉受压元件安装前，应制定焊接工艺评定作业指导书，并进行焊接工艺评定。焊接工艺评定合格后，应编制用于施工的焊接作业指导书。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]