[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111888":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1111888,787,1,"单选题","吊装方案主要编制依据中的施工技术资料不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","被吊设备设计制造图",false,{"key":16,"text":17,"correct":14},"B","设备基础施工图",{"key":19,"text":20,"correct":21},"C","吊装参数表",true,{"key":23,"text":24,"correct":14},"D","设计会审文件","本题考查的是吊装方案。施工技术资料：主要包括被吊装设备（构件）的设计制造图、设备基础施工图、设备平立面布置图、相关专业施工图、设计会审文件、施工现场地质资料等。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]