[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1111867,787,1,"单选题","安装基准线和基准点的测设符合要求的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按设备基础的定位轴线来测定机械设备的纵、横中心线",false,{"key":16,"text":17,"correct":14},"B","测设中心线刻画再混凝土基础上",{"key":19,"text":20,"correct":14},"C","标高基准点埋设在设备底板下面的基础表面",{"key":22,"text":23,"correct":24},"D","连续生产线设备安装标高基准点采用预埋标高基准点",true,"按建筑物的定位轴线来测定机械设备的纵、横中心线并标注在中心标板上， 不少于纵、横两条。标高基准点一般埋设在基础边缘且便于观测的位置。不允许埋设在设备底板下面的基础表面。标高基准点：简单的标高基准点一般作为独立设备安装的基准点；预埋标高基准点主要用于连续生产线上的设备在安装时使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]