[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111832,786,2,"多选题","沥青结构层的施工方法有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","层铺法",true,{"key":16,"text":17,"correct":14},"B","路拌法",{"key":19,"text":20,"correct":21},"C","滑模摊铺法",false,{"key":23,"text":24,"correct":21},"D","轨道摊铺法",{"key":26,"text":27,"correct":14},"E","热拌热铺法","ABE","【考点】沥青结构层的施工方法。 沥青路面按施工方法分为层铺法、路拌法和厂拌法；层铺法是分层洒布沥青、分层铺撒矿料和碾压的方法修筑路面（主要路面层铺式沥青表面处治和沥青贯入式两种）；路拌法是在施工现场以不同方式将冷料热油或冷料拌和摊铺和压实的方法；厂拌法是集中设置拌和基地，采用专门设备，将具有规定级配的矿料和沥青加热拌和，然后将混合料运至工地热铺热压或冷铺冷压的方法。选项C、D均属水泥路面施工方法。故本题正确选项应为“ABE”。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]