[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111828":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111828,786,2,"多选题","（2019年）根据《公路工程建设项目招标投标管理办法》，关于招标投标的说法，错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","初步设计文件批准后，方可开展施工监理招标",false,{"key":16,"text":17,"correct":18},"B","已选定的特许经营项目投资人依法能够自行施工时，可以不进行招标",true,{"key":20,"text":21,"correct":18},"C","招标人可设置最低投标限价和最高投标限价",{"key":23,"text":24,"correct":18},"D","公路工程勘察设计招标不采用综合评估法进行评标",{"key":26,"text":27,"correct":14},"E","招标人以分包的工作量规模作为否决投标的条件，属于对分包的歧视性条款","BCD","本题考查的是公路工程施工招标投标管理相关规定。已通过招标方式选定的特许经营项目投资人依法能够自行施工时，可以不进行招标，故选项B错误。招标人不得规定最低投标限价，故选项C错误。公路工程勘察设计和施工监理招标，应当采用综合评估法进行评标，对投标人的商务文件、技术文件和报价文件进行评分，按照综合得分由高到低排序，推荐中标候选人，故选项D错误。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]