[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111820":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111820,786,2,"多选题","对施工材料成本的现场控制一般有()等方面的控制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","采购保管",false,{"key":16,"text":17,"correct":14},"B","场外运输",{"key":19,"text":20,"correct":21},"C","场内二次转运",true,{"key":23,"text":24,"correct":21},"D","操作损耗",{"key":26,"text":27,"correct":21},"E","材料发放","CDE","对材料成本控制，一是要以预算价格捞控制材料的采购成本；二是对材料的数量进行控制；同时通过实行“限额领料”来控制材料领用数量，并控制工序施工质量，争取一次合格，避免因返工而造成材料损耗。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]