[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111817":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111817,786,2,"多选题","（2020年真题）关于公路工程施工测量管理的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","对设计平面控制桩和高程控制桩等逐一进行确认接收，做好记录，办理交接桩签认手续",true,{"key":16,"text":17,"correct":14},"B","完成复测后，编制复测成果报告，经监理、设计单位签字确认后使用",{"key":19,"text":20,"correct":14},"C","在设计控制网点的基础上进行加密时，相邻加密桩点间保证通视且间距不宜超过300m",{"key":22,"text":23,"correct":24},"D","水准点加密时，沿路线每300m应有一个水准点",false,{"key":26,"text":27,"correct":14},"E","导线复测时，同一建设项目相邻施工段的导线应闭合，并满足同等精度要求","ABCE","P214-217 选项D错误：沿路线每500m宜有一个水准点。在结构物附近、高填深挖路段、工程量集中及地形复杂路段，宜增设水准点。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]