[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111798,786,2,"多选题","施工组织设计中，施工总体部署的主要内容有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建立施工管理机构",true,{"key":16,"text":17,"correct":14},"B","划分各参与单位的施工任务",{"key":19,"text":20,"correct":21},"C","制定主要分项工程的施工方案",false,{"key":23,"text":24,"correct":14},"D","安排施工顺序",{"key":26,"text":27,"correct":21},"E","制定资源需求计划","ABD","主要考察的是铲运机的适用，施工总体部署的主要内容有：(1)建立施工管理机构.(2)施工任务划分：根据工程划分WBS(WorkBreakdownStructure，工作分解结构）,划分各参与施工单位的工作任务及施工阶段，明确总包与分包、各施工单位之间分工与协作的关系，确定各单位的主要工程项目和次要工程项目。(3)施工顺序：要在总体上确定各单位工程、分部工程、分项工程的施工顺序，分清主次，统筹安排，保证重点，兼顾其他，以确保工期，并实现施工的连续性和均衡性。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]