[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111797":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111797,786,2,"多选题","（2019年）公路施工过程基本组织方法除流水作业法外，还有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","矩阵作业法",false,{"key":16,"text":17,"correct":14},"B","时差作业法",{"key":19,"text":20,"correct":14},"C","班组作业法",{"key":22,"text":23,"correct":24},"D","平行作业法",true,{"key":26,"text":27,"correct":24},"E","顺序作业法","DE","本题考查的是公路工程进度计划的编制特点。公路施工过程基本组织方法有顺序作业法、平行作业法、流水作业法。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]