[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111796":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111796,786,2,"多选题","某施工单位因延误了工期，需压缩某工作的持续时间，可采用的技术措施有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加每天的劳动力数量",false,{"key":16,"text":17,"correct":18},"B","改变施工工艺",true,{"key":20,"text":21,"correct":14},"C","用物质激励以提高工作效率",{"key":23,"text":24,"correct":18},"D","采用先进的施工机械",{"key":26,"text":27,"correct":14},"E","增加工作面","BD","压缩关键工作持续时间和调整关键工作逻辑关系的措施。3.技术措施：(1)改进施工工艺和技术，缩短工艺技术间歇时间(如混凝土的早强剂等）；(2)改变施工方法以缩短持续时间(如现浇方案改为预制装配）；(3)采用先进的施工方法和施工机械。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]