[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111778":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111778,786,2,"多选题","隧道施工方法有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","新奥法",true,{"key":16,"text":17,"correct":14},"B","盾构法",{"key":19,"text":20,"correct":21},"C","移动模架法",false,{"key":23,"text":24,"correct":21},"D","整体现浇法",{"key":26,"text":27,"correct":14},"E","传统矿山法","ABE","隧道施工方法包括：①新奥法；②传统的矿山法；③隧道掘进机法；④盾构法；⑤明挖法；⑥盖挖法；⑦浅埋暗挖法；⑧地下连续墙。选项C、D均属于桥梁施工方法。故本题正确选项应为“ABE”。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]