[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111769":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111769,786,2,"多选题","承台混凝土浇筑直接倾卸高度超过2m时，应通过（ ）等设施下落。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","串筒",true,{"key":16,"text":17,"correct":18},"B","滑槽",false,{"key":20,"text":21,"correct":14},"C","溜槽",{"key":23,"text":24,"correct":14},"D","振动溜管",{"key":26,"text":27,"correct":18},"E","宽口料斗","ACD","考点:混凝土施工。超过2m时，应通过串筒、溜管（槽）或振动溜管（槽）等设施下落；倾落高度超过10m时，应设置减速装置。@##",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]