[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111766":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111766,786,2,"多选题","（2019年）为便于支架拆卸，选用落模设备考虑的主要因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工队伍资质",false,{"key":16,"text":17,"correct":18},"B","支架结构形式",true,{"key":20,"text":21,"correct":18},"C","需要的卸落量",{"key":23,"text":24,"correct":14},"D","施工季节",{"key":26,"text":27,"correct":18},"E","承受的荷载大小","BCE","该试题考点已过期，新版教材已变化，为保证试卷完整性，仅供考生参阅。本题考查的是常用模板、支架和拱架的施工。为便于支架和拱架的拆卸，应根据结构形式、承受的荷载大小及需要的卸落量，在支架和拱架适当部位设置相应的木楔、木马、砂筒或千斤顶等落模设备。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]