[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111762":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111762,786,2,"多选题","桥梁支架施工时需对支架进行设计计算，其计算荷载应主要考虑()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","梁体混凝土重量",true,{"key":16,"text":17,"correct":14},"B","支架、模板重量",{"key":19,"text":20,"correct":14},"C","人、料、机及风荷载",{"key":22,"text":23,"correct":14},"D","保证设施荷载",{"key":25,"text":26,"correct":27},"E","预压试验荷载",false,"ABCD","支架的布置根据梁截面大小并通过计算确定以确保强度、刚度、稳定性满足要求，计算时除考虑梁体混凝土重量外，还需考虑模板及支架重量，施工荷载（人、料、机等），作用在模板、支架上的风力，以及其他可能产生的荷载（如雪荷载，保证设施荷载）等。而“预压试验荷载”是在对支架进行预压时施加的荷载，不属于在支架设计时所考虑的荷载，所以不应选E。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]