[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111760":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111760,786,2,"多选题","关于人工挖孔桩施工要求的说法，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","孔口处护圈应与地面齐平",false,{"key":16,"text":17,"correct":14},"B","挖孔桩施工应按桩号顺序依次开挖",{"key":19,"text":20,"correct":21},"C","施工前应制定安全专项施工方案",true,{"key":23,"text":24,"correct":14},"D","井孔内电缆应为防水绝缘电缆，照明电压不应大于36V",{"key":26,"text":27,"correct":21},"E","挖孔作业时，应经常检查孔内空气情况","CE","主要考察的是挖孔粧施工，挖孔粧施工的安全要求(1)挖孔作业，应详细了解地质、地下水文情况，不得盲目施工。(2)施工前应制订专项安全技术方案并应对作业人员进行安全技术交底。(3)每作业班组不得少于3人，作业人员必须身体健康，井下作业人员必须戴安全帽、安全带，安全绳必须系在孔口。(4)井孔内设100W防水带罩灯泡照明，电压为12V低电压，电缆为防水绝缘电缆。(5)人工挖孔作业时，应经常检查孔内空气情况。孔内遇到岩层需爆破时，应专门设计，宜采用浅眼松动爆破法，严格控制用药量并在炮眼附近加强支护，孔深大于5m时必须采用电雷管爆破，并按国家现行的《爆破安全规程》GB6722—2014中的有关规定办理。孔内爆破后应先通风排烟15min并经检查无有害气体后施工人员方可下井继续施工。@##",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]