[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111755,786,2,"多选题","连续梁桥上部结构采用支架现浇施工时，确定支架搭设高度应考虑的因素有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","梁体内模尺寸",false,{"key":16,"text":17,"correct":18},"B","梁体设计标高",true,{"key":20,"text":21,"correct":18},"C","支架的弹性变形",{"key":23,"text":24,"correct":18},"D","支架的非弹性变形",{"key":26,"text":27,"correct":18},"E","基础的允许下沉量","BCDE","(二)现浇支架施工要求：1.支架应进行设计和计算，并经审批后方可施工。2.支架的强度、刚度和稳定性等要求应符合《公路桥涵施工技术规范》JTG\u002FTF50—2011有关条款的规定。3.支架的弹性、非弹性变形及基础的允许下沉量应满足施工后梁体设计标高的要求。4.整体浇筑时应采取措施，防止梁体不均匀下沉产生裂缝，若地基下沉可能造成梁体混凝土产生裂缝时，应分段浇筑。5.当在软弱地基上设置满布现浇支架时，应对地基进行处理，使地基的承载力满足现浇混凝土的施工荷载要求。无法确定地基承载力时，应对地基进行预压，并进行部分荷载试验。6.对高度超过8m的支架，应对其稳定性进行安全论证，确认无误后方可施工。7.施工时应对支架的变形、位移、节点和卸架设备的压缩及支架基础的沉降等进行观测，如发现超过允许值的变形、变位，应及时采取措施予以调整。梁体内模尺寸，跟支架搭设高度没有直接关系。选BCDE",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]