[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111749":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111749,786,2,"多选题","新建水泥混凝土路面面板抗滑构造施工方法有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","人工拉槽",true,{"key":16,"text":17,"correct":14},"B","硬刻槽",{"key":19,"text":20,"correct":14},"C","拉毛机拉槽",{"key":22,"text":23,"correct":24},"D","铺砂",false,{"key":26,"text":27,"correct":24},"E","铣刨机铣刨","ABC","摊铺完毕或精整平表面后，宜使用钢支架拖挂1～3层叠合麻布、帆布或棉布，洒水湿润后做拉毛处理。人工修整表面时，宜使用木抹。当日施工进度超过500m时，抗滑沟槽制作宜选用拉毛机械施工，没有拉毛机时，可采用人工拉槽方式。特重和重交通混凝土路面宜采用硬刻槽，凡使用圆盘、叶片式抹面机整平后的混凝土路面、钢纤维混凝土路面必须采用硬刻槽方式制作抗滑沟槽。选项D是用于检测抗滑构造深度的一种方法，选项E一般用于沥青路面再生。故本题正确选项应为“ABC”。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]