[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111739":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111739,786,2,"多选题","为防止水泥稳定碎石基层裂缝病害，可采取的预防措施有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在保证强度的情况下，适当增加水泥稳定碎石混合料的水泥用量",false,{"key":16,"text":17,"correct":18},"B","碎石级配应接近要求级配范围的中值",true,{"key":20,"text":21,"correct":18},"C","严格控制集料中粘土含量",{"key":23,"text":24,"correct":18},"D","养护结束后应及时铺筑下封层",{"key":26,"text":27,"correct":14},"E","宜在气温较低的季节组织施工","BCD","预防措施有：①控制水泥质量，在保证强度的情况下，应适当降低水泥稳定碎石混合料的水泥用量；②碎石级配应接近要求级配范围的中值；③应严格控制集料中粘土含量；④应严格控制加水量；⑤混合料碾压成型后及时洒水养护，保持碾压成型混合料表面的湿润；⑥养护结束后应及时铺筑下封层；⑦宜在春季末和气温较高的季节组织施工，工期的最低温度在5℃以上，并在第一次冰冻到来之前一个月内完成，基层表面在冬期上冻前应做好覆盖层（下封层或摊铺下面层或覆盖土）。增加水泥稳定碎石混合料的水泥用量，不利于裂缝预防，反而增加裂缝，选项A错误；宜在春季末和气温较高的季节组织施工，而非宜在气温较低的季节组织施工，选项E错误。故本题正确选项应为“BCD”。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]