[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111734":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111734,786,2,"多选题","关于路基冬期施工的说法，正确的有（ ）。（2017年真题）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","半填半挖地段、挖填方交界处不得在冬期施工",true,{"key":16,"text":17,"correct":18},"B","动气填筑路堤，应按横截面全宽平填，每层松铺厚度应比正常施工增加20%~30%",false,{"key":20,"text":21,"correct":14},"C","当填筑至路床底面1M时，碾压密实后应停止填筑，在顶面覆盖防冻保温层",{"key":23,"text":24,"correct":14},"D","冬期过后必须对填方路堤进行补充压实",{"key":26,"text":27,"correct":14},"E","河滩地段可利用动气水位低，开挖基坑修建防护工程","ACDE","考点:路基冬期施工。选项B，正确的说法应为“冬期填筑路堤，应按横断面全宽平填，每层松铺厚度应比正常施工减少20%～30%，且松铺厚度不得超过300mm”。@##",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]