[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111725":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111725,786,2,"多选题","填石路堤施工前，应通过修筑试验路段确定的参数有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","松铺厚度",true,{"key":16,"text":17,"correct":14},"B","压实机械型号及组合",{"key":19,"text":20,"correct":14},"C","压实速度及压实遍数",{"key":22,"text":23,"correct":24},"D","压实度",false,{"key":26,"text":27,"correct":14},"E","沉降差","ABCE","主要考察的是填石路基施工技术,(1)路堤施工前，应先修筑试验路段，确定满足表2B311013-2中孔隙率标准的松铺厚度、压实机械型号及组合、压实速度及压实遍数、沉降差等参数。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]