[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111723":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111723,786,2,"多选题","通过修筑填石路堤试验路段来确定的施工参数有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","松铺厚度",true,{"key":16,"text":17,"correct":14},"B","沉降差",{"key":19,"text":20,"correct":14},"C","压实速度",{"key":22,"text":23,"correct":24},"D","最佳含水量",false,{"key":26,"text":27,"correct":14},"E","压实机械型号及组合","ABCE","路床施工前，应先修筑试验路段，确定能达到最大干密度的松铺厚度、压实机械型号及组合、压实速度及遍数、沉降差等参数。故选ABCE",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]