[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111698":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111698,786,2,"多选题","公路工程建设项目验收分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","中间交工验收",false,{"key":16,"text":17,"correct":18},"B","交工验收",true,{"key":20,"text":21,"correct":14},"C","工序验收",{"key":23,"text":24,"correct":18},"D","竣工验收",{"key":26,"text":27,"correct":14},"E","开工验收","BD","2020版教材P339 公路工程验收分为交工验收和竣工验收两个阶段。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]