[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111686,786,2,"多选题","公路工程进度计划的审查要点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期和时间安排的合理性",true,{"key":16,"text":17,"correct":18},"B","计划目标的可实现性",false,{"key":20,"text":21,"correct":14},"C","施工准备的可靠性",{"key":23,"text":24,"correct":18},"D","工期安排的科学性",{"key":26,"text":27,"correct":14},"E","计划目标与施工能力的适应性","ACE","2020版教材P204 该题主要考察的是进度计划的审查要点， 进度计划的审查要点 1、工期和时间安排的合理性 2、施工准备的可靠性 3、计划目标与施工能力的适应性",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]