[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111684":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111684,786,2,"多选题","公路工程进度计划的主要形式包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":14},"B","S曲线",{"key":19,"text":20,"correct":21},"C","控制图",false,{"key":23,"text":24,"correct":14},"D","斜率图",{"key":26,"text":27,"correct":21},"E","相关图","ABD","2020版教材P200 公路工程进度计划的主要形式：1.横道图；2.S曲线；3.斜率图；4.网络图；垂直图",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]