[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111683":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111683,786,2,"多选题","要求间歇是指（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术间歇",true,{"key":16,"text":17,"correct":18},"B","总时差",false,{"key":20,"text":21,"correct":14},"C","组织间歇",{"key":23,"text":24,"correct":18},"D","空间间歇",{"key":26,"text":27,"correct":18},"E","强制时限","AC","2020版教材P201 （一）公路工程常用的流水参数1.工艺参数：施工过程数n（工序个数），流水强度v；2. 空间参数：工作面A、施工段m、施工层；3. 时间参数：流水节拍t、流水步距K、技术间歇Z、组织间歇、搭接时间。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]