[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111681,786,2,"多选题","资源需求计划主要包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","劳动力需求计划",true,{"key":16,"text":17,"correct":14},"B","材料需求计划",{"key":19,"text":20,"correct":14},"C","施工机械设备需求计划",{"key":22,"text":23,"correct":14},"D","资金需求计划",{"key":25,"text":26,"correct":27},"E","“香蕉”曲线计划",false,"ABCD","2020版教材P194 资源需求计划主要有： 劳动力需求计划；材料需求计划；施工机械设备需求计划；资金需求计划。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]