[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111680":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111680,786,2,"多选题","工程施工条件主要有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","地形地貌",true,{"key":16,"text":17,"correct":14},"B","气象条件",{"key":19,"text":20,"correct":14},"C","水文条件",{"key":22,"text":23,"correct":24},"D","工程部位",false,{"key":26,"text":27,"correct":14},"E","资源供应情况","ABCE","2020版教材P194 （2） 施工条件：地形地貌、气象、水文和地质等自然条件；资源供应情况、交通运输 及水电等施工现场条件和技术经济条件。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]