[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111673,786,2,"多选题","对“S”曲线描述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","是工程进度的表达.",true,{"key":16,"text":17,"correct":18},"B","是对质量的统计分析",false,{"key":20,"text":21,"correct":14},"C","又称为现金流动曲线",{"key":23,"text":24,"correct":14},"D","以工期为横轴",{"key":26,"text":27,"correct":14},"E","以累计完成的工程费用的百分比为纵轴","ACDE","2020版教材P200 “S” 曲线是以时间为横轴，以累计完成的工程费用的百分数为纵轴的图表化曲线。—般在图上标注有一条计划曲线和实际支付曲线，实际线高于计划线则实际进度快于计划，否则就慢； 曲线本身的斜率也反映进度推进的快慢。有时，为反映实际进度另增加一条实际完成线（支付滞后于完成 。 在公路工程中，常常将 “S” 曲线和横道图合并于同一张图表中， 称之为 “公路工程进度表” ，既能反映各分部（项） 工程的进度，又能反映工程总体的进度。 D，工期以时间表示。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]