[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111671":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111671,786,2,"多选题","施工总部署的主要内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立施工管理机构",true,{"key":16,"text":17,"correct":18},"B","编制施工工艺技术",false,{"key":20,"text":21,"correct":14},"C","施工任务划分",{"key":23,"text":24,"correct":14},"D","确定施工顺序",{"key":26,"text":27,"correct":18},"E","编制施工进度计划","ACD","2020版教材P194 施工总体部署的主要内容有：1.建立施工管理机构；2.施工任务划分；3.施工顺序。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]