[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111663":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111663,786,2,"多选题","桥梁预制构件的预制场选择需要考虑的主要因素有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","现场的地理、地形环境",true,{"key":16,"text":17,"correct":14},"B","桥梁的规模及工期",{"key":19,"text":20,"correct":14},"C","梁的运输与安装",{"key":22,"text":23,"correct":14},"D","存梁场面积",{"key":25,"text":26,"correct":27},"E","桥梁施工单位性质",false,"ABCD","2020版教材P299 预制场的布置取决于现场的面积、地形、工程规模、安装方法、工期及机械设备情况等,条件不同,布置方法差异较大。E项不涉及现场因素，其它项都与现场有关。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]