[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111662,786,2,"多选题","工程量清单中有标价的单价或总额包括了工、料、机、管理、利润、缺陷修复，税金等费用，以及合同中明示或暗示的所有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","责任",true,{"key":16,"text":17,"correct":18},"B","权利",false,{"key":20,"text":21,"correct":14},"C","义务",{"key":23,"text":24,"correct":18},"D","保险",{"key":26,"text":27,"correct":14},"E","一般风险","ACE","2020版教材P279 除非合同另有规定，工程量清单中有标价的单价和总额价均已包括了为实施和 完成合同工程所需的劳务、材料、机械、质检（自检）、安装、缺陷修复、管理、保险、 税费、利润等费用，以及合同明示或暗示的所有责任、义务和一般风险。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]