[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111661":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111661,786,2,"多选题","工程价款价差调整的主要方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","调值公式法",true,{"key":16,"text":17,"correct":14},"B","调价文件计算法",{"key":19,"text":20,"correct":21},"C","预算价格调整法",false,{"key":23,"text":24,"correct":14},"D","实际价格调整法",{"key":26,"text":27,"correct":14},"E","工程造价指数调整法","ABDE","2020版教材P289 该题主要考察的是工程价款价差调整的主要方法， 工程价款价差调整的主要方法（1）工程造价指数调整法；（2）实际价格调整法；（3）调价文件计算法；（4）调值公式法；",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]