[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111649,786,2,"多选题","标后预算按照不同的管理阶段分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目估算（直接）成本",false,{"key":16,"text":17,"correct":18},"B","项目预算（直接）成本",true,{"key":20,"text":21,"correct":18},"C","计划预算（直接）成本",{"key":23,"text":24,"correct":18},"D","实际预算（直接）成本",{"key":26,"text":27,"correct":14},"E","实际决算（直接）成本","BCD","2020版教材P269 标后预算按照不同的管理阶段，可以分为项目预算（直接） 成本、计划预算（直接） 成本、实际预算（直接）成本等。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]