[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111647":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111647,786,2,"多选题","公路工程变更包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计变更",true,{"key":16,"text":17,"correct":14},"B","进度计划变更",{"key":19,"text":20,"correct":14},"C","施工条件变更",{"key":22,"text":23,"correct":24},"D","工程质量变更",false,{"key":26,"text":27,"correct":14},"E","原招标文件和工程量清单中未包括的“新增工程”","ABCE","2020版教材P262 该题主要考察的是工程变更的内容，工程变更包括设计变更、进度计划变更、施工条件变更以及原招标文件和工程量清单中未包括的“新增工程”。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]