[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111645":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111645,786,2,"多选题","引起承包人索赔的众多因素中，比较普遍的因素有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","赶工",true,{"key":16,"text":17,"correct":14},"B","开工受阻",{"key":19,"text":20,"correct":14},"C","气候影响",{"key":22,"text":23,"correct":24},"D","施工机械故障停工",false,{"key":26,"text":27,"correct":14},"E","工程量的增加","ABCE","2020版教材P264 该题主要考察的是施工索赔管理， 在分析引起索赔的众多因素中，比较普遍的因素是赶工、开工受阻、气候影响、工程量的增减、合同条款中与索赔密切相关的工程变更、增加工程及工程进度变化引起的工期与费用的索赔。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]