[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111629":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111629,786,2,"多选题","先简支后连续梁桥的施工质量控制要点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预制拼装",false,{"key":16,"text":17,"correct":18},"B","后浇段工艺控制",true,{"key":20,"text":21,"correct":18},"C","体系转换工艺控制",{"key":23,"text":24,"correct":18},"D","后浇段收缩控制",{"key":26,"text":27,"correct":18},"E","临时支座安装与拆除控制","BCDE","2020版教材P223 连续梁桥① 支架浇筑时：支架沉降量的控制。② 先简支后连续：后浇段工艺控制、体系转换工艺控制、后浇段收缩控制、临时支座安装与拆除控制。③ 预应力梁：张拉预应力钢筋及压浆控制。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]