[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111628":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111628,786,2,"多选题","在薄壁墩与实心墩施工中，其控制要点不同之处有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","墩身与承台联结处混凝土裂缝控制",true,{"key":16,"text":17,"correct":18},"B","模板接缝错台控制",false,{"key":20,"text":21,"correct":14},"C","墩顶实心段混凝土裂缝控制",{"key":23,"text":24,"correct":18},"D","墩顶支座预埋件位置、数量控制",{"key":26,"text":27,"correct":18},"E","墩身锚固钢筋预埋质量控制","AC","2020版教材P223 （一）实心墩1．墩身锚固钢筋预埋质量控制；2．墩身平面位置控制；3，墩身垂直度控制；4．模板接缝错台控制；5．墩顶支座预埋件位置、数量控制。（二）薄壁墩1．墩身锚固钢筋预埋质量控制；2．墩身平面位置控制；3．墩身垂直度控制；4．模板接缝错台控制；5．墩顶支座预埋件位置、数量控制；6．墩身与承台联结处混凝土裂缝控制；7．墩顶实心段混凝土裂缝控制。B、D、E选项为控制要点共同处，故不符合。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]