[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111622":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111622,786,2,"多选题","现场质量检查控制包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","开工前检查",true,{"key":16,"text":17,"correct":14},"B","工序交接检查与工序检查",{"key":19,"text":20,"correct":14},"C","隐蔽工程检查",{"key":22,"text":23,"correct":14},"D","停工后复工前检查",{"key":25,"text":26,"correct":27},"E","竣工验收检查",false,"ABCD","2020版教材P220 现场工程质量检查分开工前检查、施工过程中检查和分项工程完成后的检查。 二、 现场质量检查控制。1.开工前检查；2.施工过程中检查；3.施工后检查；4.停工后复工前的检查；5.分项、分部工程完工后的检查；6.巡视检查。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]