[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111577":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111577,786,2,"多选题","隧道监控量测时，量测计划应根据（ ）等编制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","围岩条件.",true,{"key":16,"text":17,"correct":14},"B","量测项目",{"key":19,"text":20,"correct":14},"C","施工方法",{"key":22,"text":23,"correct":24},"D","监控人员素质",false,{"key":26,"text":27,"correct":24},"E","隧道长度","ABC","2020版教材P162 量测计划应根据隧道的围岩条件、支护类型和参数、施工方法以及所确定的量测目的进行编制，同时应考虑量测费用的经济性，并注意与施工的进程相适应。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]