[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1111536":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1111536,786,2,"多选题","属于造成预制梁桥预拱度偏差的原因的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","支架弹性变形混凝土梁挠度的计算有误",false,{"key":16,"text":17,"correct":18},"B","施加预应力时间差异",true,{"key":20,"text":21,"correct":18},"C","实际预应力超过设计预应力",{"key":23,"text":24,"correct":18},"D","波纹管竖向偏位过大",{"key":26,"text":27,"correct":14},"E","支架地基在荷载作用下的沉陷计算有误","BCD","2020版教材P155 预制梁，一方面由于混凝土强度的差异、混凝土弹性模量不稳定导致梁的起拱值的不稳定、施加预应力时间差异、架梁时间不一致，实际预应力超过设计预应力易引起大梁的起拱值大，且出现裂缝。施工工艺的原因，如波纹管竖向偏位过大，造成零弯矩轴偏位。所以选BCD。 AE属于现浇梁：由于支架的形式多样，对地基在荷载作用下的沉陷、支架弹性变形、混凝土梁挠度等计算所依据的一些参数均建立在经验值上，因此计算得到的预拱度往往与实际发生的有一定差距。",{"id":6,"name":31,"category":32,"favorite":33},"二建公路工程实务","建筑工程",0]